Some activities were scheduled to run concurrently. Unlike last semester, most of the Spring semester activities included calling vendors which was done by mainly one group member. Another group member did the web page editing, two did ProEngineer drawings of the concepts and another worked mainly on the presentations and necessary calculations. Some tasks were more time consuming than expected. The schedule is shown below.

Table 4 - Spring Schedule

Activity ID

Activity Description

Dates

1.0

Present Final Design

Jan. 8 - Jan. 29

1.10

Finalize Design

Jan. 8 - Jan. 15

1.20

Present: Restated Scope

Jan. 11

1.40

Manufacturing Cost

Jan. 15 - Jan. 22

1.50

Present: Restated Plan

Jan. 18

1.30

Details of Prototype Testing

Jan. 22 - Jan. 29

2.0

Prototype Testing

Jan. 29 - April 2

2.10

Create Procedure

Jan. 29 - Feb. 5

2.20

Testing

Jan. 29 - March 12

2.40

Present: Progress Report

Feb. 1

2.30

Modifications and Testing

Feb. 5 - April 2

2.60

Midpoint Review Presentation

Feb. 15

2.80

Progress Report/Presentation

March 22

2.110

Operation Manuals

April 3

3.0

Prepare Final Design

April 2 - April 6

3.20

Web Page/Final Report

April 5

3.40

Final Presentation

April 10

3.50

Project Evaluations

April 17

As shown above, testing is the major priority for the Spring 2001 semester, scheduled for approximately eight weeks from January 29 to April 2. Modifications to the design were scheduled to run concurrently to the testing. Two weeks were dedicated to preparing the final design, with dates ranging from April 2 to April 16, 2001.