Project Start Date: Tue 12/5/00
Project Finish Date: Thu 4/12/01
ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
---|---|---|---|---|---|---|
1 | Restated Scope | 3 days | Mon 1/8/01 | Wed 1/10/01 | 0% | |
2 | Restated Plan | 3 days | Mon 1/15/01 | Wed 1/17/01 | 0% | |
3 | Finalize Design | 7 days | Mon 1/15/01 | Tue 1/23/01 | 0% | |
4 | Purchase parts and materials | 7 days | Tue 1/23/01 | Wed 1/31/01 | 0% | |
5 | build prototype | 2 days | Wed 1/31/01 | Thu 2/1/01 | 0% | |
6 | test and modify prototype | 2 days | Fri 2/2/01 | Mon 2/5/01 | 0% | |
7 | install and test final model | 1 day | Tue 2/6/01 | Tue 2/6/01 | 0% | |
8 | create web page | 41 days? | Mon 1/8/01 | Mon 3/5/01 | 0% | |
9 | final design calculations | 5 days | Thu 1/25/01 | Wed 1/31/01 | 0% | |
10 | Progress report Presentation | 3 days | Mon 1/29/01 | Wed 1/31/01 | 0% | |
11 | Mid-point Review | 8 days | Mon 2/12/01 | Wed 2/21/01 | 0% | |
12 | Progress Report Presentation | 3 days | Thu 3/1/01 | Mon 3/5/01 | 0% | |
13 | Progress Report Presentation | 3 days | Mon 3/26/01 | Wed 3/28/01 | 0% | |
14 | Operation Manual | 10 days | Thu 3/15/01 | Wed 3/28/01 | 0% | |
15 | Final Report | 10 days | Thu 3/22/01 | Wed 4/4/01 | 0% | |
16 | Final Report Presentation | 5 days | Thu 3/29/01 | Wed 4/4/01 | 0% | |
17 | Project Evaluation | 4 days | Mon 4/9/01 | Thu 4/12/01 | 0% |
ID | Name | Group | Max Units | Peak Units |
---|
Task ID | Task Name | Resource Name | Work | Start | Finish | % Work Complete |
---|