Updates |
| Date |
Entry |
| 1-10-2011 |
A skeleton of the website is up. Pictures will be added to our biographies as well as a group photo for the home page soon. Looking into putting this into a table that can be scrolled through independant of the rest of the page and it will be updated weekly. Our group is waiting our materials to come in. |
| 2-10-2011 |
The extruded aluminum spray structure has been built. Waiting on the hollow aluminum and end caps to come in to finish the array. |
| 2-25-2011 |
The code to run the micro-control board has been written and tested. Working on SCI communication. Tried using labview but it is not made to run on the dragon board. |
| 3-14-2011 |
The software side of the project has been completed. Ended up using the hyperterminal to communicate with the dragon board. |
| 3-26-2011 |
All of the piping structure has been completed. Integration of the controls and piping is next and then testing. |
| 4-11-2011 |
Testing completed. Flow rate is a little lower than would have liked but the integration worked well. Final report done and operations manual soon to be completed. |