3. What was accomplished the last two weeks on individual
tasks- representative supporting data/ documents
The budget was “approved” by NASA. NASA decided to
have us order parts through them, with them shipping to us.
(Entire Team)
Purchase Orders have been placed and the first order has been
received. (Entire Team)
Arm design completed. (Dean, Tyler, James)
Testing of the charge system for the ATRV-Jr. is being
conducted. (Itiel, Luke)
Research into safety system for laboratory design and setup of
the system has been started. (Itiel, Luke)
Conference calls with Van Townsend, per his request, to discuss
ideas and presentations. (Entire Team)
|