Date | Scheduled Activities |
Sept. 8 | Project Description |
Sept. 20 | Proposal and Group Assignment Due |
Sept. 22 | Test #1 (heat transfer and fluid mechanics) |
Oct. 11 | Progress Report Due |
Oct. 20 | Test #2 |
Oct. 25 | 2nd phase Design Plan Due |
Nov. 17 | Test #3 |
Nov. 24 | 1st Presentation |
Nov. 25 | Thanksgiving holiday |
Dec. 1 | 2nd Presentation, Final Report Due |
Dec. 17 7:30-9:30 a.m. | Final Exam. |